IDFM also recalls that, since 2016, 16 billion euros have been invested in metro and train rolling stock, for 1,600 new or refurbished trainsets.
The region will spend no less than 4 billion euros on these operations. The organizing authority warns that the works will be extensive and that service interruptions will be significant, notably during the summer.
"Several interruptions are scheduled this summer in order to concentrate major works to modernize and renew the infrastructure,"IDFM said. Work on the network will intensify next summer.
The longest schedule concerns Havre-Caumartin station, served by lines 3 and 9. It will no longer be accessible at all from March 2027 until 2029.
The concourse and its mezzanine, the corridors and the platforms of both metro lines will be rebuilt. The four entrances opening onto the public street will also be refurbished, notably on Boulevard Haussmann and Rue du Havre.
The underground connections with RER A, via Auber station, and with RER E, via Haussmann-Saint-Lazare station, will also be closed.
Carrying out this work will require long nights, with an earlier end of service in the evening, and Sunday closures.
Beyond this station, lines 6, 8, 12 and 13 are benefiting from major modernization programs intended to lastingly improve their performance.
They will make it possible to modernize the driving system of lines 6 and 12, to prepare for the arrival of the MF19 on lines 8 and 13, and to continue preparatory work for the automation of line 13.
RER B will undergo two structuring operations. On the southern section, the works will prepare for the arrival of the MI20. On the northern section, they will renew essential infrastructure.